From raw land to power: How integrated planning accelerates data center development

 

Artificial intelligence (AI) is accelerating demand for data centers at a pace few could have predicted just a few years ago. As hyperscale campuses grow larger and more power-intensive, developers face increasing pressure to bring new capacity online as quickly as possible. In today’s market, speed to power determines speed to market.

But the journey from raw land to reliable operations is becoming increasingly complex. Grid constraints have utilities racing to expand transmission infrastructure and generation capacity, while developers simultaneously navigate site selection, utility planning, permitting, engineering, and a growing number of regulatory approvals and community concerns. Each workstream influences the others, and every delay ripples across the project’s critical path.

More than ever, successfully delivering a data center requires coordinating dozens of parallel efforts into a single, integrated program that maintains momentum from site acquisition to energized operations. As the AI race becomes an infrastructure race, the teams best positioned to succeed will be those that understand how every decision influences the path to reliable power.

Building momentum through due diligence

The developers that consistently move projects forward aren’t necessarily the ones that acquire sites the fastest; they’re the ones that evaluate them thoroughly. Comprehensive due diligence helps uncover everything from easements, utility constraints, and power availability to environmental needs, community sentiment, and long-term expansion opportunities.

The goal is more than simply reducing risk, it’s about gaining momentum and saving time. Every constraint identified before acquisition or design is an opportunity to begin planning sooner and keep the critical path moving forward. By enabling multiple workstreams to advance together, due diligence becomes the foundation for faster, more coordinated project delivery.

Aligning utilities and approvals through early engagement

Finding a viable site is only the beginning. Securing reliable power and obtaining local approvals are two of the biggest drivers of a project’s schedule, and they’re deeply interconnected. Beyond available grid capacity or water supply, developers must navigate an increasingly complex entitlement process before utilities can move projects forward. In many cases, utility providers require key local approvals before executing service agreements or committing to infrastructure investments.

That challenge has only grown as hyperscale data centers become larger and more visible. Projects that once moved through local approvals with relatively little attention now face increased public scrutiny, more extensive review processes, and, in some markets, temporary development moratoriums as local governments evaluate the long-term impacts and community benefits.

That doesn’t mean progress has to wait. Early engagement allows project teams to understand the utility requirements, coordinate infrastructure planning, explore alternative power strategies, and identify constraints while public engagement and entitlements continue.

Bridging the gap to reliable power

AI has fundamentally changed the scale of power required for data center development. Not long ago, 10- to 20-megawatt facilities were common. Today, campuses are increasingly planned for hundreds of megawatts, with some exceeding a gigawatt of demand—roughly the output of a nuclear power plant. To deliver that level of power, connecting to the grid is still the most reliable and scalable solution.

Yet even after selecting a site, navigating permitting and approvals, and advancing utility coordination, it can still take years for permanent grid capacity to become available. Utilities don’t move at the same pace as AI demand, which forces us to think strategically about how to reach operations while long-term transmission and generation projects are completed.

For many developers, this means evaluating alternative power strategies such as on-site natural gas generation, battery storage, or renewable sources like wind and solar. While each of these solutions can also involve long lead times and their own permitting and approval processes, they provide benefits beyond accelerating project schedules. They also strengthen long-term power resilience by providing additional layers of redundancy and operational flexibility.

Hyperscale facilities are engineered around what’s known as “four nines” reliability, meaning 99.99% uptime, or less than one hour of allowable downtime over an entire year. They need to keep running during scheduled maintenance and repairs, and they can’t go offline if an unexpected power disruption occurs. So, in addition to bridging the gap until permanent grid connections, alternative power sources become a critical component of long-term operational reliability in a data center’s power strategy.

As power demands continue to grow, securing reliable and redundant sources is an ongoing consideration throughout the development lifecycle. Every decision, from site selection and due diligence to engineering, permitting, and construction, influences the path to energized operations. Keeping those decisions aligned is what ultimately separates projects that maintain momentum from those that fall behind schedule.

Program management as a competitive advantage

Connecting to reliable power is a thread that runs through every phase of development. Decisions made during due diligence influence utility strategy. Utility timelines shape engineering and permitting. Public approvals affect service agreements. Every discipline influences the path to energized operations, making coordination just as critical as technical expertise.

Few developers have the internal bandwidth to coordinate every consultant, utility, permitting agency, and stakeholder across multiple campuses. As data centers continue to expand in scale and complexity, success is increasingly determined by the ability to coordinate all disciplines effectively to maintain momentum across the development program.

Just as importantly, experienced teams understand the local landscape—from permitting timelines and utility requirements to labor markets and community dynamics. Sometimes the most valuable insight comes from knowing who to call or recognizing where a planned transmission upgrade could reshape the project schedule.

That’s where program management creates the greatest value. It combines technical expertise, local knowledge, and disciplined coordination to identify issues early, maintain momentum, and give developers the confidence to focus on delivering the next generation of AI infrastructure.

The path forward

Developing the infrastructure to support the new generation of data centers has become one of the defining challenges of the AI era. As power demands continue to grow and project timelines become increasingly compressed, the path from raw land to energized operations will require closer coordination than ever before.

Developers that embrace an integrated, programmatic approach won’t just be better positioned to overcome today’s challenges, they’ll be better prepared for what comes next. As the AI race continues to reshape infrastructure development, demand for power will continue to grow and regulatory environments will continue to evolve. The ability to efficiently move projects from raw land to reliable power will remain a defining competitive advantage for developers that can maintain momentum and coordinate every phase of the development lifecycle.

About the Author

Jason Minock

Senior Development Manager, Renewables

Jason has 25 years of experience in land planning and development for real estate and energy developers. He currently oversees the program management for one of Atwell’s largest energy clients.

Capital is back, but smarter. Why due diligence wins in 2026.

 

Tighter lending and investment criteria are raising the stakes for due diligence and rewarding the developers who treat it as a competitive advantage, not a formality.

Investment is returning. Data centers continue to capture headlines and capital, but the momentum doesn’t stop there. Advanced manufacturing, logistics, multi-family, and select retail segments are all seeing renewed activity after moving at a slower pace in the past few years. Developers who spent that time waiting on the sidelines are starting to move again.

But the capital coming back into the market in 2026 doesn’t look like the capital that left it. It’s smarter. More deliberate. And far less forgiving of surprises.

What “smarter capital” actually means

“Smarter capital” has become shorthand for a shift everyone in commercial real estate and development can feel but hasn’t fully named. Ask what it actually means, and the answer isn’t new technology or a vastly different financial structure. It’s a sharper, more disciplined process which includes a lot more time and attention spent on due diligence before capital ever moves.

Call it smarter capital or call it what it really is: patient capital. Lenders and equity partners have more time on land contracts than they did a few years ago, and they’re using it. That extra runway means more emphasis on vetting, more boxes checked, and more confidence that a project can move smoothly through the development process once capital is committed.

The fundamentals haven’t changed. Good dirt, used for its highest and best purpose, still draws capital. What’s changed is the patience investors have for ambiguity. With interest rates and construction costs largely leveled off, capital is gravitating toward certainty. The preference is projects with fewer unknowns, clearer paths to entitlement, and fewer reasons for a deal to stall. Smarter capital isn’t chasing home runs. It’s looking for singles, doubles, and triples, deals it can trust to perform with less volatility along the way.

Why the questions are coming earlier

Lenders and investors aren’t necessarily asking new questions; however, they’re asking the same questions earlier, and in more detail. Investors today have more information at their fingertips than ever before, and that access has changed expectations. A passive investor who once relied more on gut instinct can now research a sector in minutes and walk into a conversation sounding informed, even without deep industry expertise.

The result is a capital-raising process where the depth of diligence required on the front end has increased substantially. Developers and project sponsors who can’t answer detailed technical questions early are finding their deals take longer to fill a capital stack or don’t get funded at all. In 2026, the developers winning capital aren’t necessarily the ones with the boldest vision. They’re the ones who’ve already de-risked it.

Where the new scrutiny shows up

Some specific areas of due diligence have become non-negotiable, regardless of asset type:

  • Power and water capacity. The conversation around data centers has put utility infrastructure under a microscope, and that scrutiny is spilling over into advanced manufacturing, cold storage, and any facility with a meaningful automation footprint. Investors want to know what else is being developed nearby, whether the local utility can deliver the power load required, and how that impacts the project’s schedule well before capital is committed.
  • Entitlement and community support. Discretionary approvals can make or break a project’s timeline, and one contentious public hearing can color how capital views an entire submarket. Investors increasingly want evidence that a development team has done the upfront work with community leaders and stakeholders, not just the engineering.
  • Site complexity. Infill and redevelopment opportunities (i.e., repurposed malls and underused retail corridors) carry a different diligence profile than greenfield sites. Greenfield work centers on geotechnical conditions, floodplains, wetlands, and utility capacity. Infill work centers on navigating an existing entitlement and community context. Smarter capital understands that distinction and expects development partners to have a clear path to success.

None of this is about reinventing due diligence. It’s about doing it earlier, more thoroughly, and with answers ready before anyone needs to ask twice.

Where AI fits, and where it doesn’t

The advancement of AI is definitely part of why capital has gotten smarter. It has made it easier for investors, including those without deep sector history, to ask sharper questions sooner. That’s a real shift in how capital is raised, and it rewards developers who treat strong technical groundwork as a front-end investment rather than a box to check later.

AI is also changing how project teams work. Used well, AI can accelerate research, permit tracking, and data gathering. Used carelessly, it can produce answers that sound confident but don’t hold up under review. The fundamentals still have to drive the decision: what is the investment thesis, what is the risk tolerance, and what does the data show. AI can speed up how a team gets there. It can’t make the call and it can’t build the relationships to make a project successful from conception through construction.

Why due diligence wins in 2026

This is where early technical validation earns its place in the process not as a formality, but as the work that determines whether a deal moves smoothly through entitlement, financing, and construction. Without that, a project may stall at the first hard question.

Atwell’s nationwide, multidisciplinary team is built to deliver that validation quickly. Our diversity across geography and service lines means a developer working through site selection for an advanced manufacturing facility can get a fast read from our power team on utility capacity, while our GIS team pulls together the mapping and site data investors are asking for, often before the question is fully on the table.

Our goal as strategic consultants to our clients is to see and identify issues or risk before they are asked by internal or external stakeholders and pivot quickly or provide options for paths forward. Regardless of what our scope is we approach every project with the mindset of how can we make our clients’ life easier while helping them get from point A to point B in their project faster.

That speed matters because every land contract and capital raise runs on the clock. Time spent chasing answers after the fact is time most developers don’t have. Our team functions as an extension of a client’s team: understanding their schedule, their benchmarks, and the specific points where lenders and equity partners are likely to push, then making sure those answers are ready well before they’re needed.

Good opportunities haven’t disappeared. Capital is back in the market in 2026, and it’s smarter about where it lands. The developers who move fastest from site control to funded, shovel-ready deals will be the ones who treat due diligence as the foundation of the process, not a hurdle at the end of it. In a market built on patient, disciplined capital, due diligence isn’t just protection. It’s the advantage.

About the Author

Jesse Conrad

Vice President

Jesse Conrad serves as a Vice President with more than 16 years of experience leading residential, commercial, industrial, recreational, and educational development projects of varying sizes. He specializes in civil engineering and land development, helping clients navigate complex projects from planning and design through permitting and approval. His expertise includes site grading, accessibility compliance, erosion and sediment control, utility design, stormwater management, and coordinating with local, county, and state agencies to help projects move forward efficiently.

The spaces in between: How commercial retail connections become community foundations

 

In growing communities, development often starts with a central hub that drives momentum and creates new opportunities for the businesses, services, and neighborhoods around it. Retail development helps shape the identity of a community by creating gathering spaces, supporting daily needs, and influencing how people experience the area. Alongside housing, these commercial centers help establish the foundation for how a community will function and grow.

Creating successful retail developments requires thoughtful planning and strong collaboration between community stakeholders, developers, municipalities, utility providers, engineers, contractors, and investors. Market knowledge, technical expertise, and execution all play an important role, but long-term success is often driven by something less visible: the power of connection.

In communities experiencing rapid growth, these connections help ensure retail spaces are positioned to operate successfully from day one and continue supporting the community well into the future.

The most successful development teams often create value in the spaces in between the formal scopes of work, where coordination, timing, and industry relationships can shape a project’s long-term success. Projects that move efficiently from concept to completion often depend on stakeholders being aligned early, even before challenges fully emerge. Because teams working across the full development lifecycle can see projects from multiple perspectives, they are often able to identify opportunities others may miss. Atwell applies this approach by helping connect the people, resources, and expertise needed to keep projects moving forward, even when a clear path does not yet exist. Through our family of companies, we provide resources spanning the full project lifecycle, and we bring the right people together to create solutions and build new possibilities. These connections often happen outside formal project scopes, in conversations or introductions that bring the right expertise together at the right moment.

The “spaces in between”: Turning process insight into opportunity

Commercial retail projects face obstacles when there is disconnect across teams, processes, or community requirements. These “spaces in between” can create delays, inconsistencies, and missed opportunities if teams are not aligned.

For example, a developer may manage projects across the country and need support tailored to the unique requirements of each community. When different teams operate independently without collaboration, the project experience and outcomes can vary. Atwell functions as a national team with local expertise to create a consistent approach across every project. We connect teams, partners, and services to help turn ideas into reality while maintaining accuracy from start to finish. Additionally, a brand may need to follow the same rules, guidelines, and processes, no matter where they are operating. Our in-house teams take the time to understand those standards so we can provide seamless support across markets and communities.

If additional expertise is needed, we connect clients with the right teams across our network and family of companies. We also make sure everyone involved understands the project goals, requirements, and next steps from the start.

Instead of just advocating for our clients, we help connect them with the people, resources, and solutions needed to keep projects moving forward and bring them to completion by truly understanding their goals.

Creating connections that drive better development outcomes

Our team excels at thinking beyond traditional solutions. By combining technical expertise with strong industry relationships, we often identify opportunities others might miss.

Jesse Conrad, Vice President at Atwell, recently shared an example from a recent initiative. “I was meeting with a national home builder that was planning a new residential community,” said Conrad. “During our conversations, they shared that one of their biggest goals was creating a place where residents could truly live, work, and shop without leaving the area. Around the same time, one of our commercial clients noted also looking for opportunities to bring shopping and dining options into growing markets and specifically that submarket. It became clear that the two organizations could benefit from knowing each other.”

“Rather than treating those conversations separately, we made the introduction and helped bring both sides to the table early in the planning process. What started as two independent projects quickly turned into a collaborative vision for a more connected community. Moments like that show the value of understanding our clients’ broader goals and knowing when the right connection can create new opportunities for everyone involved, creating win-win opportunities for our clients, the community and it’s future residents.”

While these started as separate projects, it ultimately led to a new working relationship between two organizations that shared the same end goal. In industries as integrated as commercial retail, these relationships often become the foundation for future projects.

Why Atwell is positioned to make these connections

Atwell works across the full project lifecycle, offering solutions that start from due diligence and continue through opening day, with consistency, program knowledge, and value provided every step of the way.

Our family of companies expands the expertise we can bring to every project. Because we collaborate with developers, utilities, municipalities, and contractors nationwide, we often see opportunities to connect partners who can solve challenges together.

This perspective helps us identify opportunities others may overlook by connecting ideas, expertise, and resources across organizations to create stronger commercial retail experiences and more connected communities.

About the Author

Jesse Conrad

Vice President

Jesse Conrad serves as a Vice President with more than 16 years of experience leading residential, commercial, industrial, recreational, and educational development projects of varying sizes. He specializes in civil engineering and land development, helping clients navigate complex projects from planning and design through permitting and approval. His expertise includes site grading, accessibility compliance, erosion and sediment control, utility design, stormwater management, and coordinating with local, county, and state agencies to help projects move forward efficiently.

The data center boom is real. The grid gap is real. The good news? So are the solutions

 

The data center development boom is unlike anything the infrastructure industry has seen in decades. AI adoption has dramatically accelerated demand for power, and developers are racing to secure land, permits, and utility capacity at a pace the grid and broader utility ecosystem were never designed to support. The result is a complex challenge that is forcing developers to rethink not just where they build, but how they power their facilities from the moment they break ground.

The tension is straightforward: developers want power now, and the grid can’t deliver it fast enough. Understanding why and what options exist in the interim is essential for any developer.

The grid constraint is reshaping development strategy

Connecting to the utility grid remains the most cost-effective long-term power solution for data centers. Grid power, purchased at commercial or industrial rates, is significantly cheaper than building and maintaining on-site generation. The problem is the timeline. Depending on the market, a meaningful grid connection can take several years when you factor in land acquisition, infrastructure planning, permitting, and construction. For a developer who wants to be operational “tomorrow,” that timeline is untenable.

Compounding the delay is a significant community relations challenge for utilities and developers. In many states and municipalities, data centers have become a flashpoint for community opposition, not necessarily because of the facilities themselves, but because of misperceptions around electricity rates and environmental impact. Many residents fear that data centers will drive up their electricity bills, even though developers typically purchase power at separate commercial rates and do not burden the residential rate base. Utilities are caught between pursuing large commercial load growth opportunities and navigating public utility commission scrutiny, ratepayer concerns, and political pressure around infrastructure expansion. Water consumption has also become a growing point of public scrutiny, particularly in water-stressed regions, even as newer facilities increasingly rely on closed-loop and more efficient cooling technologies. The perception gap between environmental impact and community concern remains wide, adding another layer of complexity to development projects.

Bridge power: A growing menu of options

Given the grid access timeline, a wide range of “behind-the-meter” and temporary power solutions have emerged. These are not new concepts, but the scale and urgency of data center demand have elevated them into mainstream planning conversations. Here is where the market currently stands:

Fuel cells. Natural gas-powered fuel cells have become one of the more prominent bridge solutions. Companies have established a meaningful foothold in the data center market. Fuel cells offer a relatively clean, scalable power source, and while they come at a cost premium over grid power, they are increasingly viewed as a viable interim or supplementary solution.

Gas turbines. Gas-fired turbines have historically been a go-to for on-site power generation, but the market is currently constrained. Turbine manufacturers are facing significant backlogs driven by simultaneous demand from data centers, power generation facilities, and natural gas compressor stations. Developers who want turbines need to place orders and commit capital well in advance, with delivery timelines that rival the grid itself.

Battery storage. Battery energy storage systems are an increasingly common component of the bridge power toolkit, often deployed in combination with other generation sources. They provide flexibility and resiliency, though they are not often a standalone solution for the sustained power loads that large-scale data centers require.

Diesel and dual-fuel generators. Diesel and propane generators remain in the mix as backup and supplementary sources. Their capacity limitations, however, make them better suited to redundancy roles than primary power for hyperscale or large regional facilities.

Wind and solar. Renewable generation is viable in the right circumstances, but the land footprint required to generate meaningful megawatts can be substantial. Developers who can integrate a solar or wind component into a larger site plan may find these options increasingly attractive, particularly as permitting for smaller distributed sites becomes more common.

The decision framework: Cost, speed, and long-term fit

For most developers, the conversation around bridge power comes down to a tradeoff: is the cost of a temporary or permanent behind-the-meter solution worth it compared to waiting for grid access? Well-capitalized developers like large hyperscalers and institutional players often have the balance sheet to pursue either path. The decision becomes more nuanced for mid-market developers working with tighter margins.

The key variables are rarely just financial. Speed to market, site-specific constraints, local regulatory dynamics, and the developer’s long-term operational strategy all factor in. A developer with a site near an existing substation faces fundamentally different considerations than one in a greenfield location with no nearby infrastructure. Getting the analysis right from the outset before land is committed or capital is deployed is where strategic planning makes the biggest difference.

Looking ahead at a market in transition

The current pace of data center development is extraordinary, but it will likely moderate somewhat. The land-acquisition frenzy of the past 18 to 24 months is beginning to encounter the natural limits of grid capacity, equipment supply chains, and public acceptance. The market is not stopping as AI adoption has created a demand curve that is not going to reverse but it is maturing.

One meaningful shift on the horizon is a move toward smaller, more efficient facilities. As chip technology advances, data centers will be able to do more with less space and less power. A portfolio of five 20-acre facilities may ultimately replace the need for a single 100-acre hyperscale campus. That model is both easier to permit and more resilient from an infrastructure standpoint. The underlying demand for power will continue to grow; the physical footprint required to meet it may not grow at the same rate.

The importance of creating a strategy to meet the needs of today

Navigating the intersection of land, power, permitting, and infrastructure planning requires an integrated strategy from the outset.

The most effective engagements begin early, well before a site is selected, before a power strategy is committed, and before regulatory exposure is locked in. Our role as a strategic partner is to help developers understand the full landscape of options, stress-test their assumptions, and build a plan that is grounded in what is actually achievable in a given market and timeline.

The challenges shaping data center development today are not going away. But for developers who approach them with the right team and the right plan, they are navigable.

About the Author

Brent Straub

Senior Director

Brent Straub is a strategic operations and program executive with more than 15 years of experience leading technical operations, field execution, and organizational transformation across critical infrastructure sectors. He specializes in directing large-scale natural gas distribution and transmission programs, bringing deep expertise in pipeline replacement, integrity management, and regulatory compliance across PHMSA, DOT, and FERC requirements. Brent is recognized for scaling programs across complex, multi-state environments and aligning engineering, construction, and operational teams to deliver safety-critical infrastructure with consistency and discipline.

The power of presence in commercial retail development: Reflections from ICSC Las Vegas


By Carlos Casas

The energy at ICSC Las Vegas

As a first timer at ICSC Las Vegas this year, I was impressed by the sheer size of the event. I previously attended ICSC events in both San Antonio and Dallas, so I expected strong networking opportunities and valuable conversations. However, Las Vegas brought together professionals from across the country in a way that felt uniquely energizing. To describe the energy there, it was a buzz of networking, collaboration, and conversations. Attendees included developers, brokers, engineers, planners, retailers, and consultants who are all helping shape the future of retail development.

ICSC Las Vegas felt both fast-paced and purposeful. My schedule was filled with meetings, which led to great conversations about future opportunities, and helped deepen my professional relationships through face-to-face interactions. The event reinforced something that is easy to overlook in the industry: connection is still critical in commercial retail development.

The impact of relationship-based collaboration 

The event reminded me that there is still so much value in just being in the same room as clients, colleagues, and industry partners. During my time at the event, I had the opportunity to meet with people who I have worked with across projects but had never met in person. Those conversations were meaningful to me. They created a deeper personal foundation that will positively impact the relationships I have both inside and outside of the office.

Commercial retail development projects depend on coordination between many moving parts. Project success requires collaboration between teams managing land development, surveying, engineering, planning, permitting, utilities, and construction timelines. Strong relationships are what bridge the gaps to help processes move forward more efficiently. These relationships help people communicate more openly, solve problems faster, and better understand goals.

That human element was one of the biggest takeaways from the event. Relationships remain the foundation behind successful projects, even in an industry driven by technical expertise and execution. In-person conversations allow for stronger communication and establish an understanding that can’t always be replicated virtually.

The human side of the industry 

ICSC also highlighted how important collaboration is as the retail industry continues to evolve. Developers and retailers are navigating hurdles like shifting consumer expectations, changing markets, redevelopment opportunities, and growing communities that need thoughtfully planned commercial spaces. To overcome these challenges, both technical knowledge and partnerships between professionals who can work together effectively are necessary.

At Atwell, we see how that collaboration plays out every day. Our teams work alongside clients from the earliest planning stages through project completion to help navigate challenges and keep projects moving forward. Events like ICSC create opportunities to strengthen those relationships beyond the day-to-day work of meetings, deadlines, and deliverables. This time we get to spend together in person allows for more meaningful conversations and helps us deeper understand how to support clients as their needs continue to evolve.

The business value of being present   

Another takeaway from the event was the level of passion shared across the industry. The professionals attending ICSC weren’t just there to exchange business cards or discuss transactions. There was genuine enthusiasm around creating spaces that support businesses, strengthen communities, and drive economic growth. That energy was visible from discussions about new retail trends to conversations about redevelopment and expansion opportunities across the country.

Maintaining presence will remain essential as the commercial retail industry continues to move quickly. Schedules will continue to fill up, projects will continue to grow in complexity, and technology will continue changing how teams communicate. Events like ICSC Vegas are a reminder that in-person interaction still plays an important role in building momentum and moving projects forward successfully.

The takeaways   

Leaving ICSC, I am walking away with a renewed appreciation for the value of connection within this industry. The face-to-face experiences I had throughout the event reinforced how important relationships are in the work we do. Strong partnerships help projects succeed and are often strengthened most through time spent together. ICSC Las Vegas was a great reminder that behind every commercial retail project are people working together to solve challenges, create opportunities, and build lasting relationships that continue well beyond the event itself.

About the Author

Carlos Casas

Director

Carlos Casas serves as the Director of the Commercial Land Development Division for Atwell’s Central Region, specializing in programmatic land development initiatives for QSR and retail clients. With 14 years of industry experience, Carlos is known for building trusted client relationships and fostering collaboration across teams and stakeholders. His relationship-driven approach and commitment to team excellence have been instrumental in delivering successful programs and supporting long-term growth. 

The grid can’t keep up: Understanding the U.S. power transmission crisis

The United States is experiencing its most significant electricity demand growth in decades. AI data centers, semiconductor manufacturing facilities, electric vehicles (EVs), renewable energy projects, and more are all adding load to a grid that was built for a different era. At the center of every conversation around whether the grid can keep pace is one foundational issue: power transmission infrastructure.

Understanding what power transmission is, why it matters, and what makes it so difficult to deliver at the scale and pace the country needs is essential for anyone working in or alongside the energy, utilities, and infrastructure sectors today.

What is power transmission?

Power transmission refers to the large-scale movement of electricity from where it is generated to where it is consumed. Once electricity is generated, whether at a natural gas plant, wind farm, solar facility, or nuclear station, it must be transported to where it will be consumed.. That transmission is often across significant distances, before it reaches homes, businesses, data centers, manufacturing facilities, and factories.

This movement happens across a network of high-voltage transmission lines, electrical substations, and switching equipment that collectively form what most people commonly call “the electrical grid.” Transmission is distinct from power distribution, which handles the final delivery of electricity at lower voltages within local communities. Transmission functions as the electrical system’s long-haul highway network.

The U.S. grid is divided into three major interconnections: the Eastern Interconnection, the Western Interconnection, and the Texas Interconnection (ERCOT). Within those broad zones, regional transmission organizations (RTOs) manage the real-time balance of supply and demand across their respective footprints.

Why does power transmission matter so much right now?

The short answer is because U.S. electricity demand is rising rapidly, and the infrastructure that moves power across the country has not kept pace.

For roughly two decades following the 2008 financial crisis, U.S. electricity demand was essentially flat. Efficiency gains in appliances and lighting, along with slow economic growth in some regions, kept load growth modest. Utilities and grid planners were able to operate in an environment where incremental upgrades were generally sufficient.

That environment no longer exists.

Several forces are converging to drive electricity demand higher at a pace that is straining both grid modernization efforts and physical infrastructure:

  • AI data centers and hyperscale computing growth: Hyperscale data centers and AI training facilities require enormous, continuous power loads of hundreds of megawatts at a single site. This sector alone is adding gigawatts of new demand across multiple regions simultaneously.
  • Advanced manufacturing and industrial electrification: Semiconductor production, battery manufacturing plants, and other industrial facilities are coming online with power requirements measured in the hundreds of megawatts. Many of these facilities require substation construction, transmission upgrades, and grid infrastructure improvements before they can even open.
  • Transportation electrification: The shift toward electric vehicles, along with electrification of rail, port operations, and commercial fleets, is adding distributed but substantial new load to the grid.
  • Renewable energy integration: Wind and solar resources are often located far from population centers requiring significant high-voltage transmission capacity to deliver that power where it is needed.
  • Aging grid infrastructure: Much of the existing U.S. transmission system was built decades ago. Aging equipment, thermal constraints, and reliability concerns are limiting how much power existing lines can carry, even before the new demand is factored in. At the same time, utilities are under increasing pressure to improve grid resilience against extreme weather events and physical system disruptions, adding further urgency to transmission investment.

The result is a gap between what the grid can currently move and what the economy increasingly needs it to move. Closing that gap requires expanding electric transmission capacity at a scale and speed that industry has not attempted.

Key challenges slowing transmission expansion

If the need for more transmission is clear, why is it so difficult to build? Several interconnected challenges make transmission one of the most complex energy infrastructure sectors in the country.

  • Transmission routing complexity

    Transmission lines must travel across real terrain, through multiple jurisdictions, and past properties owned by thousands of individual landowners. Identifying a viable corridor while avoiding environmental sensitivities, significant community impact, and remaining economically feasible, is not a simple exercise.Routing decisions require detailed analysis of environmental constraints (including wetlands, habitat, cultural resources), land use patterns, existing infrastructure, and topography. When those analyses happen in sequence rather than in parallel, the process takes longer and produces more modifications. When they are integrated early, transmission development projects move faster and encounter fewer surprises along the way.
  • Permitting and regulatory approvals

    Most transmission projects require a Certificate of Public Convenience and Necessity (CPCN) or equivalent state regulatory approval before construction can begin. These proceedings involve public hearings, expert testimony, environmental review, and regulatory deliberation. The process can span years, particularly when routing alternatives are not well-defined or when there may be opposition to a project or route.Federal permitting requirements add additional layers of complexity, particularly for projects crossing federal land or affecting sensitive resources.
  • Land access and right-of-way acquisition

    Securing legal access to the land a transmission line will cross is one of the most time-consuming and relationship-intensive parts of the transmission line development process. Easements must be negotiated with individual landowners, many of whom have no prior experience with utility easements and may be skeptical of the project.Find out more about this essential step by visiting one of our recent posts on right-of-way (ROW).
  • Interconnection queues and backlogs

    Before a new generation or transmission project can connect to the grid, it must go through an interconnection study process managed by the appropriate grid operator. In most regions, these queues are severely backlogged right now, even up to multiple years in part because many regions are attempting to evaluate large volumes of proposed generation and load simultaneously. New generation resources waiting for interconnection approval often represent far more capacity than the grid can physically accommodate, which complicates transmission planning and creates uncertainty for developers trying to build quickly to meet demand.
  • Supply chain and workforce constraints

    Even when permitting and land access are resolved, bringing a transmission project to construction requires transformers, conductors, towers, and other critical grid equipment that is currently in tight supply.This means that the projects able to move from development into procurement and construction fastest, because they have resolved permitting and land access efficiently, have a meaningful competitive advantage in securing the equipment and crews they need.

The bigger picture

Power transmission is about connection. It connects generators to consumers, remote resources to population centers, and the energy system we have today to the energy system the economy is demanding for tomorrow.

The challenges involved are real and substantial. But they are not insurmountable. They are engineering and management problems, and they can be addressed through clear-eyed analysis, early action, disciplined coordination, and the kind of experience that comes from having navigated the issues before.

As electricity demand continues to rise and the pressure to expand U.S. transmission infrastructure capacity intensifies, the question is not whether this infrastructure will be built. It will be. The question is which power transmission projects move efficiently, and which ones will stall given the expertise needed to bring projects to completion.

Why disciplined real estate and land development wins when markets shift

The current real estate and land development market is operating under a layer of uncertainty that can quickly evolve. Factors such as interest rate fluctuations, inflation, immigration policy changes, construction labor shortages, rising development costs, operating expenses, and the accelerating impact of artificial intelligence (AI) are creating a fog over the path forward. They have the potential to create a market disruption even if conditions remain relatively stable today.

As we move through 2026, many developers and owners remain focused on growth, continuing to advance projects with confidence. Still, uncertainty is influencing how decisions are made, encouraging a more measured and strategic approach to development. What we have found is that the developers who succeed when volatility does emerge will be those who are already navigating the fog by building with discipline and exploring creative solutions to achieve their end goals.

Fundamentals are fundamental for a reason 

Even in stable periods, strong fundamentals are what prepare projects to withstand future market shifts. Disciplined real estate and land development begins with choosing the right location for your project. Following demand drivers, such as job growth, infrastructure investment, demographic trends, and long-term community viability, will lead to the right location choice. From there, success depends on realistic underwriting, a phased execution of the project, and a deep understanding of the market

Looking ahead, several trends could influence future shifts. In the current market, labor force growth is slowing, largely due to changes in immigration policy. From 2020 to 2024, the majority of U.S. population growth came from immigration. As immigration slows, overall economic growth may moderate, potentially influencing housing demand.
Construction labor shortages are also expected to intensify. Current demographics show that growth in the Sun Belt states is slowing, while some population growth is returning to historically slower-growth regions such as the Snow Belt states. Climate factors, healthcare costs, and the housing “lock-in effect,” where homeowners keep lower mortgage rates, are influencing mobility and reducing relocation rates.

Growth is being redistributed across different markets. Developers who understand these shifts today will be better positioned to respond if and when conditions tighten. A smart developer will look at which populations are growing, where they are relocating, and what types of housing those communities will need.

Ask the right questions  

We’ve found that due diligence is key to success. Successful developers will also spend time understanding their end user. Asking questions, such as, “Who are we building for? What problem does this project solve? And will that need still exist five, ten, or twenty years from now?” Staying on top of trends and paying attention to demographics will lead to smart decision-making. The real estate industry has now shown that what was once considered niche can quickly become essential.

Project sectors such as data centers, senior housing, medical offices, student housing, and self-storage are not only here to stay, but play critical roles in supporting societal needs. They serve digital infrastructure, the aging population, healthcare demands, and housing supply constraints. The current rise of formerly niche sectors and subsectors to essential property types is opening the door to new options that may be essential in the decades ahead. These sectors also demonstrate how quickly demand can evolve, reinforcing the importance of building with flexibility in mind.

Disciplined developers do not build for the next quarter. They build for the next generation.

Patience is key  

When volatility does enter the market, it often rewards patience and creates opportunities for developers who value resilience. Reacting to short-term market swings or acting on assumptions will not pay off in the long-term. Instead, developers should spend time stress-testing their assumptions and prioritizing projects that align with long-term demand and operational sustainability.

When periods of uncertainty occur, they can reduce competition, recalibrate land pricing, and encourage municipalities to partner more closely with experienced development teams. For firms prepared with capital, strong relationships, and the right internal expertise, these moments can lay the groundwork for the next cycle of growth.

Move with intention and collaboration 

Disciplined development does not mean slowing down but rather moving forward with intention. Intentional decision-making starts with identifying resilient geographies and sectors that align with changing demographics, advancing technology, and shifting consumer demands. These insights help developers build a clear plan for the future.

That planning becomes even more critical for larger or more complex developments, where early decisions can significantly impact risk, cost, and long-term performance. Developers should establish a thoughtful phasing strategy that allows projects to progress in manageable stages, helping preserve capital while maintaining flexibility as market conditions evolve.

A strategic approach to infrastructure is equally important. Designing systems to scale over time, rather than building everything upfront in phase one, can reduce unnecessary upfront costs and align investment with actual demand. Together, these considerations reinforce the value of proactive, disciplined planning from the outset.

Once that plan is in place, coordinating early across disciplines helps projects move forward by identifying risks early and managing costs more effectively.

Navigating change 

Market conditions will inevitably shift over time, but disciplined developers prepare for that reality rather than reacting to it. That discipline shows up in the partners developers choose and the flexibility they build into their projects. Having the right service providers is a critical component.

A civil engineer who approaches a project with a developer’s mindset can identify opportunities to reduce costs without compromising performance, from minimizing retaining walls and excessive over-excavation to avoiding unnecessarily deep utilities. Thoughtful site design that balances cut and fill can significantly reduce earthwork costs and improve overall project efficiency, helping keep projects financially viable while still meeting design and regulatory requirements.

At the same time, versatile zoning serves as another key lever for navigating uncertainty. Securing broader entitlements expands the potential buyer pool and positions a development to adapt as market conditions shift. Mixed-use zoning or a flexible Planned Development framework allows developers to pivot between uses, whether residential, commercial, or industrial, without restarting the entitlement process. This flexibility reduces risk and helps maintain momentum, enabling projects to respond to evolving demand and capture new opportunities as they emerge.

Developers who plan for change and have a long-term strategy are better positioned to stay resilient across cycles. They plan through uncertainty rather than trying to outrun it, recognizing that cycles are inevitable and that lasting value is created by teams who remain steady as conditions fluctuate. Keeping a close eye on demographics, labor trends, and emerging sectors is essential to making informed decisions that hold up over time.

In the end, success is less about responding to today’s conditions and more about being prepared for tomorrow’s shifts. Developers who take this approach are better positioned to manage risk, control costs, and create projects that hold their value over time.

About the Author

Travis Bousquet

Director

With more than 30 years of experience, Travis oversees land development projects for various clients, from planning and design to entitlement and permitting. He is passionate about creating sustainable and innovative designs that enhance the communities and environments where we work.

Why right-of-way is the most important schedule driver in pipeline projects

By Gary Bland, Director, Atwell

When a gas utility or pipeline company decides to expand its system, the first instinct is to focus on engineering, route design, pipe specs, construction timelines. But experienced project teams know that a different workstream quietly drives the entire schedule: Right-of-way (ROW) acquisition. Get it right, and a project moves efficiently from planning to construction. Get it wrong, and costs escalate, timelines slip, and community relationships fracture in ways that are difficult to repair.

What ROW acquisition involves

At its core, ROW acquisition is the process of securing legal agreements and rights, typically in the form of an easement or surface lease, for a pipeline to cross private land and permit for crossing public land. Unlike a fee purchase, an easement allows the landowner to retain ownership and continue using their property; it simply grants the pipeline operator the right to install, operate, maintain, and access the line in a defined location. Once the pipeline is in the ground, it is unseen and landowners can farm over it, pave over it, and continue using the surface as before, as long as their use does not hinder the operation and maintenance of the pipeline.

But the work involved in getting there is anything but simple. A large pipeline project can cross hundreds or even thousands of individual parcels, each with its own ownership structure, title history, liens, and stakeholder dynamics. The ROW team must research every parcel, identify every interest holder, make initial contact with landowners, secure survey access, accompany field crews, and negotiate easement agreements, all while serving as the public face of the project.

There is also a construction phase where ROW agents remain active during construction to notify landowners ahead of crew arrivals, manage any surface damage claims, and resolve issues that may arise if equipment strays outside its permitted footprint.

Why ROW is a critical path activity

In project planning, a “critical path” activity is one where any delay directly impacts the overall project schedule. ROW acquisition earns that designation for several reasons.

First, construction cannot begin until the easements and permits are secured. No easement, no pipe in the ground. Second, ROW timelines are inherently unpredictable. Landowner negotiations can stall, title research can surface unexpected complications, and eminent domain proceedings, when necessary, add legal timelines that no team controls. Third, cost implications are significant. Easement acquisition costs, appraisal fees, legal expenses, and potential condemnation proceedings must all be estimated and budgeted well in advance, often years before a shovel hits the ground.

Finally, landowner and community opposition is a consistent source of project friction. As Gary Bland, Director at Atwell in the Houston office, notes “Pipeline projects aren’t always the most popular thing to introduce into a community. It’s a necessary and important function though in cities, towns and rural communities everywhere.” That reality shapes everything about how a ROW campaign should be planned and executed. Proactive, transparent engagement with affected property owners and community leaders is one of the most powerful tools a project team has.

Essential strategic steps before field deployment

By the time a ROW agent knocks on the first door, the outcome of the campaign is often already set.  Effective pre-deployment preparation includes several interconnected activities. Route analysis and landowner identification using GIS and public data to evaluate alignment options, estimate parcel counts, assess property types and values, and identify existing infrastructure corridors that might reduce the footprint on undisturbed land. Title research and ownership verification ensure that when a ROW agent sits across the table from a landowner, they understand every interest in that property (ownership, mortgages, liens, and other encumbrances) that could affect the agreement. Cost estimation must account not just for today’s land values but projected values across a multi-year project timeline.

Community and stakeholder outreach, ideally beginning with elected officials and community leaders, ensures that key voices hear the project’s story directly. Bland is direct on this point: ” The worst outcome is when community leaders hear about a project from concerned constituents instead of directly from you. Hearing it from you first sets the right tone from the start.” Stakeholders who feel informed and respected are far more likely to facilitate, rather than oppose, a project moving forward.

The advantage of integrated services

One factor that meaningfully improves ROW outcomes is the integration of land, survey, engineering, and environmental services under a single coordinated project team. These disciplines are deeply interdependent. ROW agents must secure survey access before field crews can mobilize. Surveyors need title information to thoughtfully plan their work. Land acquisition teams need finalized survey plats before they can execute binding agreements with landowners.

When these functions operate in silos, with separate vendors pursuing their own timelines, handoffs break down. As Bland describes it: “You’re often going to have a breakdown. They’re not focused on working with others but rather on keeping their tasks on time.”

By contrast, when land, survey, and environmental teams are aligned from day one, the project moves as a single, coordinated effort rather than  a collection of competing priorities. Data is shared in real time, schedules are aligned, and accountability is clear, giving clients greater confidence that every piece of the project is moving forward together. Bland notes that success and trust come from that kind of execution: “Projects are successful when all disciplines work closely and that’s often how we see long-term relationships grow.”

Long term projects illustrate the complexity of ROW

A current Atwell engagement illustrates this at scale. A gas distribution utility is planning a trunk line system of more than 300 miles, designed to serve the region’s continued outward growth. The project will cross approximately 3,000 parcels and is expected to span several years, with construction advancing in preplanned annual segments determined by growth projections.

The work currently underway is precisely the kind of pre-deployment preparation described above: building GIS-based ownership inventories, routing alignments to minimize impact, engaging appraisers for multi-year cost projections, and beginning outreach to community leaders. The utility’s public-facing profile has made stakeholder communication a priority and that posture has created space to approach the work the right way. “They’re really focused on their public reputation and quality engagement,” Bland notes, “so it allows us to spend more time and effort to try to make this effort a win for the community.”

Preparation is the project

ROW acquisition is not a checkbox, it’s a sustained, relationship-driven discipline that shapes every aspect of a pipeline project. Teams that treat it as a strategic function, and invest early, consistently outperform those that treat it as an afterthought. In a business where projects take years and mistakes are costly, that difference isn’t minor, it’s everything.

About the Author

Gary Bland

Director

Gary Bland serves Atwell as a Director, based in Houston, Texas. Bland has nearly three decades of experience, with deep knowledge of Land and Right-of-Way (ROW), project management, permitting, easement, and property acquisition, surveying, construction, and environmental assessment. With a wealth of experience in major oil and gas projects, Bland supports Atwell’s focus on pipeline and electric transmission projects.

Data center trends in 2026: How AI infrastructure policy impacts development

In recent years, data center development has been driven by land availability, power access, and fiber connectivity. Today, regulations and policy are emerging as a leading factor and often shape project viability even before these fundamentals.

This shift is accelerating with the emergence of “Stargate,” a federal initiative focused on expanding artificial intelligence (AI) infrastructure across the United States. These projects are pushing data center campuses beyond hundreds of megawatts into the gigawatt range and higher, with up to $500 billion in planned investment by 2029. As a result, governments, utilities, and communities are rethinking how they plan for and respond to this scale of growth.

Because of this rapid momentum, data center development regulations are surging as well. In 2025 alone, more than 200 state-level bills were introduced addressing energy use, water consumption, zoning, and other aspects of data center development.

This marks a fundamental shift for developers. Policy is now central to project strategy and must be addressed early to avoid costly permitting delays. At Atwell, we work with clients early in the process to evaluate policy risk alongside data center site selection and infrastructure considerations, helping clients focus on projects with strong viability.

Policy friction 

Projects that are technically feasible from an infrastructure standpoint are increasingly being delayed or stopped due to policy challenges. Multi-phase, gigawatt-scale campuses are prompting policymakers to reconsider:

  • How data centers connect to the grid
  • How infrastructure costs are shared
  • How communities absorb large-scale development

Policy is evolving in real time, increasing data center site selection policy risk for developers evaluating new markets.

Policy and project economics 

Data centers are increasingly classified as “large load” infrastructure, and demand at the scale of Stargate projects is reinforcing that classification. In response, states and utilities are introducing policies that:

  • Require developers to fund grid upgrades and interconnection costs through financial guarantees during the power commitment process
  • Establish new rate structures for high-demand users
  • Mandate participation in demand response or curtailment programs

At the same time, the scale of these projects is reshaping how energy is sourced. Massive campuses that will require lots of power are difficult to support through traditional grid expansion alone. Because of this, policymakers and utilities are exploring:

  • Behind-the-meter generation
  • Co-located energy infrastructure
  • New regulatory pathways for self-supplied power

Energy strategy is no longer just about securing capacity but about navigating AI data center infrastructure policy alongside utility and regulatory requirements. This shift requires earlier evaluation of interconnection risk, more flexible site design, and closer integration of energy infrastructure into land planning.

Emerging local policy 

While federal and state policies set the tone, local governments are playing a larger role in determining project outcomes. Stargate-scale campuses require extensive land, significant resources, and major transmission infrastructure. While these projects require significant resources, it is important to separate facts from uncertainty to support informed decision-making. These factors are drawing increased scrutiny at the local level.

In response, municipalities are:

  • Implementing halts on new data center development
  • Introducing stricter zoning and conditional use requirements
  • Linking approvals to impacts such as water use, noise, and visual scale

Data centers are becoming increasingly scrutinized and require stricter approval requirements. Approval depends on early alignment with local priorities, clear articulation of impacts, and proactive responses to community concerns. Site design is no longer just technical – it is a tool for securing approvals.

Incentive shifts 

Tax incentives have long played a role in data center development, but that model is evolving. States are reevaluating incentive programs and assessing net benefits of data center facilities on local communities.

Larger, campus-scale developments are accelerating this shift toward performance-based incentives, infrastructure-related requirements, and a greater emphasis on long-term community benefit. For developers, this means incentives are no longer assumed but negotiated based on how projects contribute to infrastructure, design, and community outcomes.

The federal-state-local tension triangle 

One of the most important realities in 2026 is that there is no single authority governing data center development. Federal agencies are beginning to treat AI infrastructure as strategically important. States oversee utility regulation and incentives for data center development, while local governments control land use and approvals.

The scale of emerging demand is putting pressure on all three levels at once, leading to policy overlaps, conflicting requirements, and uncertain timelines. As a result, policy due diligence regarding AI data center infrastructure must begin as early as site evaluation.

What happens next? 

Projects are getting larger, impacts are becoming more visible, and policy is evolving in response. Successful projects in this environment are not just well-engineered but well-positioned within the policy landscape from the start.

Developers will need to anticipate policy risk early, translate regulatory requirements into design solutions, and align infrastructure decisions with community and regulatory expectations.
The question is no longer just “Can we build here?” but “Can we build here at this scale, within this policy environment, and how should we design for it?”

Atwell helps clients navigate this by aligning planning and regulatory strategy early, separating facts from conjecture, and positioning projects for compliance and long-term success. Connect with our team to discuss how policy shifts could impact your data center project.

About the Author

Kevin Coughlin

Vice President

Kevin Coughlin serves as a Vice President with approximately 20 years of Mission Critical, Power and Industrial/Commercial experience. He currently leads several Mission Critical strategic growth initiatives and provides subject matter expertise to clients on Atwell’s integrated Land and Power services. His experience from early due diligence through engineering and construction provides the foundation to guide projects from the earliest concept stages through completion. 

The spaces in between: How the right relationships can move complex energy developments forward

 

Large, complex developments, such as data centers or advanced manufacturing facilities, require coordination among many specialists. Developers, utilities, engineers, municipalities, contractors, and investors all work together to move a project forward. Sound market knowledge, technical expertise, and proper execution are all essential, but one of the most valuable drivers of success is often overlooked: the power of connection.

In fast-growing sectors where timelines are tight and infrastructure demands are high, these connections often determine how quickly a project can move from concept to construction.

Atwell excels not only in our technical expertise but also in the spaces in between. We connect people, solve challenges, and help projects move forward even when a clear path does not yet exist. Because we support projects from concept through completion, our team often sees opportunities others may miss. Through our family of companies, we provide resources spanning the full project lifecycle, and we bring the right people together to create solutions and build new possibilities. These connections often happen outside formal project scopes, in conversations or introductions that bring the right expertise together at the right moment.

The “spaces in between”: where projects move forward 

Many projects stall not just because of technical barriers, but also because the right relationships have not yet been formed.

For example, a developer may need power solutions, and a utility may have capacity but lack a partner to execute quickly. Atwell sits at the intersection of these conversations and can introduce teams or partners who can turn a project from an idea to a reality.

In other cases, a municipality may be seeking economic growth while a developer is searching for the right location for their project. Our in-house teams leverage their industry relationships while prioritizing thoughtful community engagement to make the right introductions. When those priorities align, new opportunities emerge that benefit both the community and the project.

Our national presence with local expertise enables us to build connections at every level needed to bring a project to completion. If we do not have the solution, someone in our network or family of companies will, and we will help to make that connection. We not only advocate for our clients but also connect them with the people and resources they need to get the job done.

Creating connections that unlock opportunities 

Our team excels at thinking beyond traditional solutions. By combining technical expertise with strong industry relationships, we often identify opportunities others might miss.

James Hall, Executive Vice President of Special Projects, recently shared an example from a data center conference.

“I was wrapping up a meeting with a potential client and was running late to meet with an existing client,” Hall said. “Instead of cutting the conversation short, I suggested they join me for the next meeting because I believed their two companies should meet. This was a bit of a risky move that turned out to be the right call. The introduction created a strong connection between their two organizations and opened the door to new opportunities not just for the industry but also for our team. Sometimes thinking on your feet and bringing the right people together can make all the difference.” Moments like these happen in the spaces in between, when the right introduction at the right time brings new partnerships and projects to life.

While the conversation started as a simple introduction, it ultimately led to a new working relationship between two organizations that may not have otherwise connected. In industries as collaborative as data center development, these relationships often become the foundation for future projects.

Why Atwell is positioned to make these connections 

Atwell works across the full project lifecycle, offering solutions from site selection and due diligence to engineering, permitting, construction management, and power delivery solutions.

Our family of companies expands the expertise we can bring to every project. Because we collaborate with developers, utilities, municipalities, and contractors nationwide, we often see opportunities to connect partners who can solve challenges together.

This perspective allows us to identify connections that others may not see—linking ideas, expertise, and resources across organizations to keep projects moving forward.

Connection fuels progress 

Progress on complex projects rarely happens in isolation. It happens through collaboration, shared expertise, and relationships built over time. By working in the spaces in between—connecting the right people, ideas, and resources—opportunities can be transformed into real projects that move industries and communities forward.