The data center boom is real. The grid gap is real. The good news? So are the solutions

 

The data center development boom is unlike anything the infrastructure industry has seen in decades. AI adoption has dramatically accelerated demand for power, and developers are racing to secure land, permits, and utility capacity at a pace the grid and broader utility ecosystem were never designed to support. The result is a complex challenge that is forcing developers to rethink not just where they build, but how they power their facilities from the moment they break ground.

The tension is straightforward: developers want power now, and the grid can’t deliver it fast enough. Understanding why and what options exist in the interim is essential for any developer.

The grid constraint is reshaping development strategy

Connecting to the utility grid remains the most cost-effective long-term power solution for data centers. Grid power, purchased at commercial or industrial rates, is significantly cheaper than building and maintaining on-site generation. The problem is the timeline. Depending on the market, a meaningful grid connection can take several years when you factor in land acquisition, infrastructure planning, permitting, and construction. For a developer who wants to be operational “tomorrow,” that timeline is untenable.

Compounding the delay is a significant community relations challenge for utilities and developers. In many states and municipalities, data centers have become a flashpoint for community opposition, not necessarily because of the facilities themselves, but because of misperceptions around electricity rates and environmental impact. Many residents fear that data centers will drive up their electricity bills, even though developers typically purchase power at separate commercial rates and do not burden the residential rate base. Utilities are caught between pursuing large commercial load growth opportunities and navigating public utility commission scrutiny, ratepayer concerns, and political pressure around infrastructure expansion. Water consumption has also become a growing point of public scrutiny, particularly in water-stressed regions, even as newer facilities increasingly rely on closed-loop and more efficient cooling technologies. The perception gap between environmental impact and community concern remains wide, adding another layer of complexity to development projects.

Bridge power: A growing menu of options

Given the grid access timeline, a wide range of “behind-the-meter” and temporary power solutions have emerged. These are not new concepts, but the scale and urgency of data center demand have elevated them into mainstream planning conversations. Here is where the market currently stands:

Fuel cells. Natural gas-powered fuel cells have become one of the more prominent bridge solutions. Companies have established a meaningful foothold in the data center market. Fuel cells offer a relatively clean, scalable power source, and while they come at a cost premium over grid power, they are increasingly viewed as a viable interim or supplementary solution.

Gas turbines. Gas-fired turbines have historically been a go-to for on-site power generation, but the market is currently constrained. Turbine manufacturers are facing significant backlogs driven by simultaneous demand from data centers, power generation facilities, and natural gas compressor stations. Developers who want turbines need to place orders and commit capital well in advance, with delivery timelines that rival the grid itself.

Battery storage. Battery energy storage systems are an increasingly common component of the bridge power toolkit, often deployed in combination with other generation sources. They provide flexibility and resiliency, though they are not often a standalone solution for the sustained power loads that large-scale data centers require.

Diesel and dual-fuel generators. Diesel and propane generators remain in the mix as backup and supplementary sources. Their capacity limitations, however, make them better suited to redundancy roles than primary power for hyperscale or large regional facilities.

Wind and solar. Renewable generation is viable in the right circumstances, but the land footprint required to generate meaningful megawatts can be substantial. Developers who can integrate a solar or wind component into a larger site plan may find these options increasingly attractive, particularly as permitting for smaller distributed sites becomes more common.

The decision framework: Cost, speed, and long-term fit

For most developers, the conversation around bridge power comes down to a tradeoff: is the cost of a temporary or permanent behind-the-meter solution worth it compared to waiting for grid access? Well-capitalized developers like large hyperscalers and institutional players often have the balance sheet to pursue either path. The decision becomes more nuanced for mid-market developers working with tighter margins.

The key variables are rarely just financial. Speed to market, site-specific constraints, local regulatory dynamics, and the developer’s long-term operational strategy all factor in. A developer with a site near an existing substation faces fundamentally different considerations than one in a greenfield location with no nearby infrastructure. Getting the analysis right from the outset before land is committed or capital is deployed is where strategic planning makes the biggest difference.

Looking ahead at a market in transition

The current pace of data center development is extraordinary, but it will likely moderate somewhat. The land-acquisition frenzy of the past 18 to 24 months is beginning to encounter the natural limits of grid capacity, equipment supply chains, and public acceptance. The market is not stopping as AI adoption has created a demand curve that is not going to reverse but it is maturing.

One meaningful shift on the horizon is a move toward smaller, more efficient facilities. As chip technology advances, data centers will be able to do more with less space and less power. A portfolio of five 20-acre facilities may ultimately replace the need for a single 100-acre hyperscale campus. That model is both easier to permit and more resilient from an infrastructure standpoint. The underlying demand for power will continue to grow; the physical footprint required to meet it may not grow at the same rate.

The importance of creating a strategy to meet the needs of today

Navigating the intersection of land, power, permitting, and infrastructure planning requires an integrated strategy from the outset.

The most effective engagements begin early, well before a site is selected, before a power strategy is committed, and before regulatory exposure is locked in. Our role as a strategic partner is to help developers understand the full landscape of options, stress-test their assumptions, and build a plan that is grounded in what is actually achievable in a given market and timeline.

The challenges shaping data center development today are not going away. But for developers who approach them with the right team and the right plan, they are navigable.

About the Author

Brent Straub

Senior Director

Brent Straub is a strategic operations and program executive with more than 15 years of experience leading technical operations, field execution, and organizational transformation across critical infrastructure sectors. He specializes in directing large-scale natural gas distribution and transmission programs, bringing deep expertise in pipeline replacement, integrity management, and regulatory compliance across PHMSA, DOT, and FERC requirements. Brent is recognized for scaling programs across complex, multi-state environments and aligning engineering, construction, and operational teams to deliver safety-critical infrastructure with consistency and discipline.

The grid can’t keep up: Understanding the U.S. power transmission crisis

The United States is experiencing its most significant electricity demand growth in decades. AI data centers, semiconductor manufacturing facilities, electric vehicles (EVs), renewable energy projects, and more are all adding load to a grid that was built for a different era. At the center of every conversation around whether the grid can keep pace is one foundational issue: power transmission infrastructure.

Understanding what power transmission is, why it matters, and what makes it so difficult to deliver at the scale and pace the country needs is essential for anyone working in or alongside the energy, utilities, and infrastructure sectors today.

What is power transmission?

Power transmission refers to the large-scale movement of electricity from where it is generated to where it is consumed. Once electricity is generated, whether at a natural gas plant, wind farm, solar facility, or nuclear station, it must be transported to where it will be consumed.. That transmission is often across significant distances, before it reaches homes, businesses, data centers, manufacturing facilities, and factories.

This movement happens across a network of high-voltage transmission lines, electrical substations, and switching equipment that collectively form what most people commonly call “the electrical grid.” Transmission is distinct from power distribution, which handles the final delivery of electricity at lower voltages within local communities. Transmission functions as the electrical system’s long-haul highway network.

The U.S. grid is divided into three major interconnections: the Eastern Interconnection, the Western Interconnection, and the Texas Interconnection (ERCOT). Within those broad zones, regional transmission organizations (RTOs) manage the real-time balance of supply and demand across their respective footprints.

Why does power transmission matter so much right now?

The short answer is because U.S. electricity demand is rising rapidly, and the infrastructure that moves power across the country has not kept pace.

For roughly two decades following the 2008 financial crisis, U.S. electricity demand was essentially flat. Efficiency gains in appliances and lighting, along with slow economic growth in some regions, kept load growth modest. Utilities and grid planners were able to operate in an environment where incremental upgrades were generally sufficient.

That environment no longer exists.

Several forces are converging to drive electricity demand higher at a pace that is straining both grid modernization efforts and physical infrastructure:

  • AI data centers and hyperscale computing growth: Hyperscale data centers and AI training facilities require enormous, continuous power loads of hundreds of megawatts at a single site. This sector alone is adding gigawatts of new demand across multiple regions simultaneously.
  • Advanced manufacturing and industrial electrification: Semiconductor production, battery manufacturing plants, and other industrial facilities are coming online with power requirements measured in the hundreds of megawatts. Many of these facilities require substation construction, transmission upgrades, and grid infrastructure improvements before they can even open.
  • Transportation electrification: The shift toward electric vehicles, along with electrification of rail, port operations, and commercial fleets, is adding distributed but substantial new load to the grid.
  • Renewable energy integration: Wind and solar resources are often located far from population centers requiring significant high-voltage transmission capacity to deliver that power where it is needed.
  • Aging grid infrastructure: Much of the existing U.S. transmission system was built decades ago. Aging equipment, thermal constraints, and reliability concerns are limiting how much power existing lines can carry, even before the new demand is factored in. At the same time, utilities are under increasing pressure to improve grid resilience against extreme weather events and physical system disruptions, adding further urgency to transmission investment.

The result is a gap between what the grid can currently move and what the economy increasingly needs it to move. Closing that gap requires expanding electric transmission capacity at a scale and speed that industry has not attempted.

Key challenges slowing transmission expansion

If the need for more transmission is clear, why is it so difficult to build? Several interconnected challenges make transmission one of the most complex energy infrastructure sectors in the country.

  • Transmission routing complexity

    Transmission lines must travel across real terrain, through multiple jurisdictions, and past properties owned by thousands of individual landowners. Identifying a viable corridor while avoiding environmental sensitivities, significant community impact, and remaining economically feasible, is not a simple exercise.Routing decisions require detailed analysis of environmental constraints (including wetlands, habitat, cultural resources), land use patterns, existing infrastructure, and topography. When those analyses happen in sequence rather than in parallel, the process takes longer and produces more modifications. When they are integrated early, transmission development projects move faster and encounter fewer surprises along the way.
  • Permitting and regulatory approvals

    Most transmission projects require a Certificate of Public Convenience and Necessity (CPCN) or equivalent state regulatory approval before construction can begin. These proceedings involve public hearings, expert testimony, environmental review, and regulatory deliberation. The process can span years, particularly when routing alternatives are not well-defined or when there may be opposition to a project or route.Federal permitting requirements add additional layers of complexity, particularly for projects crossing federal land or affecting sensitive resources.
  • Land access and right-of-way acquisition

    Securing legal access to the land a transmission line will cross is one of the most time-consuming and relationship-intensive parts of the transmission line development process. Easements must be negotiated with individual landowners, many of whom have no prior experience with utility easements and may be skeptical of the project.Find out more about this essential step by visiting one of our recent posts on right-of-way (ROW).
  • Interconnection queues and backlogs

    Before a new generation or transmission project can connect to the grid, it must go through an interconnection study process managed by the appropriate grid operator. In most regions, these queues are severely backlogged right now, even up to multiple years in part because many regions are attempting to evaluate large volumes of proposed generation and load simultaneously. New generation resources waiting for interconnection approval often represent far more capacity than the grid can physically accommodate, which complicates transmission planning and creates uncertainty for developers trying to build quickly to meet demand.
  • Supply chain and workforce constraints

    Even when permitting and land access are resolved, bringing a transmission project to construction requires transformers, conductors, towers, and other critical grid equipment that is currently in tight supply.This means that the projects able to move from development into procurement and construction fastest, because they have resolved permitting and land access efficiently, have a meaningful competitive advantage in securing the equipment and crews they need.

The bigger picture

Power transmission is about connection. It connects generators to consumers, remote resources to population centers, and the energy system we have today to the energy system the economy is demanding for tomorrow.

The challenges involved are real and substantial. But they are not insurmountable. They are engineering and management problems, and they can be addressed through clear-eyed analysis, early action, disciplined coordination, and the kind of experience that comes from having navigated the issues before.

As electricity demand continues to rise and the pressure to expand U.S. transmission infrastructure capacity intensifies, the question is not whether this infrastructure will be built. It will be. The question is which power transmission projects move efficiently, and which ones will stall given the expertise needed to bring projects to completion.

The spaces in between: How the right relationships can move complex energy developments forward

 

Large, complex developments, such as data centers or advanced manufacturing facilities, require coordination among many specialists. Developers, utilities, engineers, municipalities, contractors, and investors all work together to move a project forward. Sound market knowledge, technical expertise, and proper execution are all essential, but one of the most valuable drivers of success is often overlooked: the power of connection.

In fast-growing sectors where timelines are tight and infrastructure demands are high, these connections often determine how quickly a project can move from concept to construction.

Atwell excels not only in our technical expertise but also in the spaces in between. We connect people, solve challenges, and help projects move forward even when a clear path does not yet exist. Because we support projects from concept through completion, our team often sees opportunities others may miss. Through our family of companies, we provide resources spanning the full project lifecycle, and we bring the right people together to create solutions and build new possibilities. These connections often happen outside formal project scopes, in conversations or introductions that bring the right expertise together at the right moment.

The “spaces in between”: where projects move forward 

Many projects stall not just because of technical barriers, but also because the right relationships have not yet been formed.

For example, a developer may need power solutions, and a utility may have capacity but lack a partner to execute quickly. Atwell sits at the intersection of these conversations and can introduce teams or partners who can turn a project from an idea to a reality.

In other cases, a municipality may be seeking economic growth while a developer is searching for the right location for their project. Our in-house teams leverage their industry relationships while prioritizing thoughtful community engagement to make the right introductions. When those priorities align, new opportunities emerge that benefit both the community and the project.

Our national presence with local expertise enables us to build connections at every level needed to bring a project to completion. If we do not have the solution, someone in our network or family of companies will, and we will help to make that connection. We not only advocate for our clients but also connect them with the people and resources they need to get the job done.

Creating connections that unlock opportunities 

Our team excels at thinking beyond traditional solutions. By combining technical expertise with strong industry relationships, we often identify opportunities others might miss.

James Hall, Executive Vice President of Special Projects, recently shared an example from a data center conference.

“I was wrapping up a meeting with a potential client and was running late to meet with an existing client,” Hall said. “Instead of cutting the conversation short, I suggested they join me for the next meeting because I believed their two companies should meet. This was a bit of a risky move that turned out to be the right call. The introduction created a strong connection between their two organizations and opened the door to new opportunities not just for the industry but also for our team. Sometimes thinking on your feet and bringing the right people together can make all the difference.” Moments like these happen in the spaces in between, when the right introduction at the right time brings new partnerships and projects to life.

While the conversation started as a simple introduction, it ultimately led to a new working relationship between two organizations that may not have otherwise connected. In industries as collaborative as data center development, these relationships often become the foundation for future projects.

Why Atwell is positioned to make these connections 

Atwell works across the full project lifecycle, offering solutions from site selection and due diligence to engineering, permitting, construction management, and power delivery solutions.

Our family of companies expands the expertise we can bring to every project. Because we collaborate with developers, utilities, municipalities, and contractors nationwide, we often see opportunities to connect partners who can solve challenges together.

This perspective allows us to identify connections that others may not see—linking ideas, expertise, and resources across organizations to keep projects moving forward.

Connection fuels progress 

Progress on complex projects rarely happens in isolation. It happens through collaboration, shared expertise, and relationships built over time. By working in the spaces in between—connecting the right people, ideas, and resources—opportunities can be transformed into real projects that move industries and communities forward.

 

How Atwell is deepening its roots in Nashville

 

There’s a reason that leading corporations (and engineering and infrastructure firms) are paying close attention to Nashville. The city, long known for its music scene and Southern charm, has quietly become one of the most dynamic and strategically important markets in the country. And Atwell is leaning in.

Over the past year, Atwell has been steadily enhancing its Nashville presence, building a team that now numbers close to a dozen professionals. That growth hasn’t happened by accident. It reflects a distinct recognition that Nashville sits at the intersection of several of the most active sectors in land development and civil engineering: mixed-use urban, healthcare infrastructure, and fast-moving private development. For a firm with national reach and local talent, the timing couldn’t be better.

Nashville’s appeal starts with its economics. The city has emerged as a major healthcare hub serving as home to HCA Healthcare, the largest for-profit hospital operator in the country, along with other significant operators, including Community Health Systems and Acadia Healthcare. These companies don’t just bring hospitals; they bring corporate operations and project pipelines that stretch across dozens of states.

For a national engineering firm with leading professionals that know and love Nashville, it creates a powerful dynamic: local relationships with decision-makers, combined with the ability to leverage experience across dozens of cities. It’s an efficient model that turns local presence into national productivity.

Beyond healthcare, Nashville’s core has experienced a sustained wave of mixed-use and multi-family development. Infill projects combining residential density with retail components have reshaped entire neighborhoods, attracting developers who value teams that can move quickly, communicate clearly, and manage multiple active projects simultaneously. This complex, fast-paced, client-service-oriented work is precisely the kind of market where Atwell’s culture and capabilities shine.

The foundation for Atwell’s Nashville operation was laid through years of relationship-building and market development, with team members already active in the region before the recent growth in staffing. That groundwork, which included establishing credibility, connecting with local developers, and building familiarity with the local landscape has positioned the office for accelerated growth.

One recent addition to the team reflects both the office’s momentum and the caliber of talent it is attracting. Matthew Hamby, a Nashville native and Tennessee Tech University graduate, joined Atwell as Senior Director with nearly a decade of experience in the AEC industry, along with additional consulting leadership experience. Hamby’s background spans some of the sectors with the greatest opportunity in the region. He has built deep client relationships across the Nashville development community and brings firsthand knowledge of the local market’s rhythms, players, and opportunities.

What drew Hamby to Atwell, he says, wasn’t just the work, but the culture. He was drawn to a privately owned company that prioritizes its people, its clients, and long-term relationship-building over short-term projects. “I’m a true believer that a rising tide raises all ships,” Hamby said. “Being part of a firm where the focus is on process improvement, training, and genuine client service is exactly where I wanted to be for the long haul.”

That entrepreneurial mindset and client-first philosophy aligns naturally with how Atwell operates, and it’s the kind of perspective the Nashville office will emphasize as it continues to grow. Hamby’s arrival adds senior-level depth to a team already gaining traction in the market and signals that the office is entering a new phase of development. The combination of a thriving healthcare economy, an active private development community, strong population growth, and an increasingly sophisticated urban core makes Tennessee one of the most compelling regions in the Southeast.

With an expanding local team, a growing project portfolio, and leadership that knows the market from the ground up, Atwell’s Nashville office is positioned to grow with the city and to help shape what it becomes.

Atwell expands P6 scheduling services across energy infrastructure

 

As energy projects become more complex, clear planning and coordination are essential. We have expanded our Primavera P6 (P6) scheduling services beyond traditional oil and gas projects to support renewable energy and transmission infrastructure.

This expansion reflects the evolving energy landscape and our continued delivery of practical, integrated solutions that help our clients move projects forward with confidence.

What is P6 scheduling? 

Primavera P6 is a project management and scheduling platform used to plan and manage complex projects. It helps teams:

  • Build detailed, logic-driven schedules
  • Track progress and performance in real time
  • Identify risks and critical path activities
  • Allocate resources across large programs

P6 creates a reliable, shared view of project progress from start to finish.

Expanding beyond oil and gas 

At Atwell, our teams have long used P6 scheduling to support large oil and gas developments, where multi-phase construction and regulatory requirements demanded careful planning.
Today, renewable energy and transmission projects face many of the same challenges, including coordinating multiple stakeholders, managing tight construction timelines, navigating changing regulations, and aligning work across geographically dispersed sites.

By expanding our P6 capabilities, we bring proven scheduling approaches to these growing areas of the energy market.

How we help clients succeed 

Our P6 scheduling services go beyond building project timelines. We help clients make informed decisions, reduce risk, and improve outcomes.

“We give our clients a clear path forward by identifying and addressing potential risks early in the project,” said Brittany Scott, Program Manager, Power and Energy. “By using P6 and bringing in dedicated team members with deep program knowledge, we deliver a clear, data-driven view of project status, critical path items, and potential delays—so our clients can act early and stay on track.”

Additional benefits of P6 include stronger risk management, improved coordination across teams, more efficient resource planning, and scalable support for complex programs.

Supporting the future of energy 

As the energy transition accelerates, projects are becoming more interconnected and schedule-sensitive. Our expanded P6 services bring structure and reliability to renewable and transmission projects, building on our experience in oil and gas.

We combine industry knowledge with advanced scheduling expertise to help clients navigate complexity and keep projects moving forward.

An integrated approach to project delivery 

Expanding P6 scheduling is part of how we deliver more connected, end-to-end solutions across our Oil & Gas, Renewables, and Power & Infrastructure teams.

By aligning planning, engineering, and execution, we help clients deliver projects more efficiently and predictably.

Powering what’s next: Why location, timing, and balance will shape the energy transition

 

Electricity demand in the U.S. is no longer a future discussion – it’s here, and it’s accelerating.

After more than a decade of relatively flat growth, forecasts now point to U.S. electricity demand increasing more than 40% by 2050. In some regions, that growth is happening even faster.  The drivers are clear: electrification, reshoring of manufacturing, and the explosive growth of AI and data centers.

Data centers alone could account for 7-12% of total U.S. electricity consumption by the end of the decade, according to the Department of Energy. That’s a structural shift in load – and it’s happening on compressed timelines.

At the same time, renewable energy continues to dominate new capacity additions.  In 2024, roughly 80-90% of new U.S. generation added to the grid came from solar, wind, and battery storage, with solar leading for multiple consecutive years. Today, renewables generate more than 20% of U.S. electricity – and an even larger share of what’s sitting in interconnection queues.

So, the question is no longer if demand is coming. The question is whether the industry can deliver infrastructure fast enough – and in the right places – to meet it.

Geography will determine who wins 

Not all load growth is created equal. In ERCOT, we’re seeing some of the fastest demand growth in the country, with solar and storage scaling to meet peak demand.  In the Midwest and Southeast, growth is being driven by manufacturing, EV supply chains, and population shifts.  In PJM – particularly Northern Virginia – data centers are creating concentrated, high-density load pockets that are stressing existing transmission systems.

This isn’t just about resource quality anymore.  It’s about proximity to load, transmission availability, and the reality of how long it takes to build. The projects that succeed will be the ones aligned with real demand and real grid conditions – not just the best solar irradiance or wind speeds on a map.

Timing is now the biggest risk – and opportunity 

One of the biggest disconnects in the market today is timing. Load is being announced quickly.  Infrastructure is not.

Interconnection queues across the U.S. now total multiple terawatts of generation and storage capacity.  Many projects face years of studies, permitting challenges, and upgrade requirements before they can move forward. At the same time, new load – especially data centers – is moving on aggressive timelines.  If generation shows up too early, projects stall. If it shows up too late, reliability and cost pressures increase.

Execution – not ambition – is becoming the differentiator. 

A balanced energy mix is not optional.

As demand accelerates, the conversation is shifting back toward reliability – and with that, a renewed focus on natural gas and other forms of firm, dispatchable generation. That shift is real, and it’s necessary.

The grid needs dependable capacity that can show up on demand. But that doesn’t reduce the role of renewables – it clarifies it. Renewables, natural gas, and storage are not competing priorities. They are complementary parts of a system that have to deliver power at scale, reliably, and at a reasonable cost.

At the same time, the long-term direction is hard to ignore. Even with policy shifts and changing political priorities, the fundamentals driving cleaner energy remain in place – corporate sustainability commitments, customer expectations, and the simple reality that emissions and environmental impact don’t pause for election cycles. You don’t have to agree on every aspect of climate policy to recognize where this is going. The energy system is getting cleaner over time – not all at once, and not in a straight line – but steadily. The real work is making sure we build a system that is both reliable today and sustainable over the long term.

Turning demand into real progress 
There is a real opportunity in front of us. Renewables and storage are now among the lowest-cost sources of new generation in many markets.  Battery storage capacity alone has grown more than tenfold in the past five years, fundamentally changing how we think about reliability and peak demand. But none of that matters if projects can’t get built.

Delivering on this moment requires alignment – between developers, utilities, regulators, and infrastructure partners. It requires a clear understanding of where load is actually materializing, when it will come online, and what it will take to serve it. Because in today’s market, success isn’t just about developing projects. It’s about developing the right projects – in the right places – at the right time. That’s how we turn load growth into real, buildable progress – and continue moving toward a more resilient and diversified energy future.

About the Author

Jason Utton

Senior Vice President

Senior Vice President of Atwell’s Power Group, Jason Utton has been developing renewable energy projects for more than 17 years, with experience in wind, solar, and battery storage projects across the country. He currently provides large scale investment and development clients with business goal setting, renewable portfolio optimization, and capital deployment strategies.

The U.S. grid’s historic crossroads: Meeting surging electricity demand through transmission expansion

 

The U.S. electric grid stands at a historic crossroads. After two decades of stagnant demand, electricity consumption is surging, driven by AI data centers, semiconductor fabrication, and widespread electrification. The Department of Energy projects a 57 percent expansion in interregional transmission capacity by 2035, signaling a generational shift in how the grid must be planned and built.

In the Midwest, MISO’s (Midcontinent Independent System Operator) $21.8 billion Long-Range Transmission Plan Tranche 2.1 represents the largest grid expansion in decades.  These projects are large, complex, and highly visible.  Experience shows that their success or failure is often determined long before construction begins.

The importance of aligning early to avoid dreaded project delays

Transmission projects rarely fail because of steel, conductor, or substations. They stall because of misalignment early in development when routing decisions, permitting strategies, land access, and stakeholder expectations are still fluid. In today’s environment, delays at this stage are costly, public, and difficult to recover from.

Through Atwell’s work on complex, transmission corridors, we have learned that the most significant risks tend to cluster early. When routing, environmental review, survey access, title clarity, and stakeholder engagement are treated as separate efforts, projects lose momentum precisely when certainty is most needed. Fragmentation creates blind spots, rework, and missed opportunities to address issues before they harden into opposition or regulatory delay.

The projects that move forward most smoothly share a common trait: early integration across disciplines, with decisions made using a shared understanding of constraints, risks, and downstream impacts.

Our experience extends across the complete sequence of activities that determine project success, and based on extensive history, integration of the key efforts plays a vital role:

  • Routing and GIS analysis – Evaluating alternative corridors using environmental, cultural, and land-use constraints to identify viable paths
  • CPCN strategy – Managing the complete Certificate of Public Convenience and Necessity process, from stakeholder engagement through testimony and compliance
  • Survey services – Multi-crew capacity delivering defensible boundary mapping, topographic surveys, and GIS-integrated parcel exhibits
  • Environmental studies – Wetland delineations, species surveys, cultural assessments, and agency coordination ensuring regulatory compliance
  • Title services – Comprehensive title reviews identifying and resolving encumbrances that could derail ROW acquisition
  • Land acquisition – Experienced agents securing permissions, negotiating easements, and managing landowner outreach across multi-state corridors

What experience has taught us about what really drives success

Across completed and ongoing transmission efforts, several patterns have emerged.

First, routing decisions improve dramatically when GIS analysis, environmental constraints, and land-use realities are evaluated together, not sequentially. Early comparison of alternative corridors using real data rather than assumptions reduces later re-routing, strengthens CPCN filings, and improves defensibility with regulators and stakeholders.

Second, survey and environmental work are not just technical steps; they are risk-management tools. Accurate, defensible base mapping and timely field studies reduce uncertainty for engineers, regulators, and landowners alike. Projects that invest early in these foundations experience fewer surprises and smoother transitions into permitting and ROW acquisition.

Third, title clarity is often underestimated until it becomes a problem. Unresolved encumbrances, access gaps, or ownership issues can derail schedules late in development. Experience has shown that identifying and addressing title risk early materially improves acquisition timelines and financing confidence.

Finally, stakeholder engagement works best when it is proactive and informed by data. Communities and landowners respond more constructively when they see that alternatives were evaluated, impacts were considered, and concerns were anticipated, not after decisions are locked in. Early transparency builds trust and reduces the likelihood of opposition escalating during formal proceedings.

Perspective and partnership

From a client perspective, early-phase transmission work is not about checking boxes, it is about protecting schedule, budget, and credibility. Competitive RFPs, CPCN processes, and regulatory reviews increasingly reward teams that can demonstrate readiness, coordination, and foresight. The ability to show that routing alternatives were explored, environmental risks were understood, land access was planned, and stakeholder concerns were addressed early is now a differentiator, not a luxury.

For utilities and developers operating in MISO’s footprint, this is especially important. Tranche 2.1 projects will be scrutinized not only for cost and engineering, but for how well risk is managed across land, environment, and public interface. Early decisions compound quickly, for better or worse.

A Perspective Built on Integration

Atwell’s role in these projects has reinforced a simple conclusion: the early phase determines everything that follows. Integration is not about efficiency for its own sake; it is about creating clarity in a process that is inherently complex and high-stakes.

Our experience across Michigan, Wisconsin, Minnesota, Illinois, Indiana, and Missouri has shaped a delivery approach centered on integration, transparency, and anticipation of risk. That perspective—earned through real projects, real constraints, and real stakeholder environments—is what we bring to each new corridor.

As Tranche 2.1 advances and additional portfolios emerge, Atwell knows that the need for thoughtful, early-phase coordination will only grow. The projects that succeed will be those that treat early development not as a preliminary step, but as the foundation for long-term success.

 

About the Author

Courtney Schmidt

Vice President

Courtney has managed and provided technical expertise to programmatic efforts across the country for over 22 years. She has passion and experience in building teams across geographies and disciplines, siting facilities, and managing development and operations activities for clients.

Seven megatrends shaping Power & Energy in 2026

 

The power and energy market has never lacked capital, technology, or ambition. What it has lacked, and continues to lack heading into 2026, is time. Electric load is growing faster than the grid can respond. Policy is moving slower than markets. Interconnection queues are overwhelmed. Communities are more engaged, more skeptical, and more willing to stop projects outright. And capital, while abundant, is becoming far more selective.

This year, success will hinge less on bold forecasts and more on execution discipline. The next cycle will reward projects that are well-sited, grid-aware, and realistically deliverable – and punish those built on outdated assumptions.

From Atwell’s vantage point, working across generation, storage, transmission, and large-load infrastructure nationwide, seven megatrends are already reshaping where capital flows and which projects get built.

1. Load growth is real – but geography & timing matter more than headlines

There is no longer serious debate about electricity demand growth. Data centers, AI workloads, electrification, reshoring, and population growth are pushing the system harder than it has been pushed in decades. The Department of Energy (DOE) estimates that data centers alone could increase national electricity consumption by 7-12% by the end of the decade, with the vast majority of that growth concentrated in a limited number of regions rather than spread evenly across the country.

What remains misunderstood is where and when that load actually materializes.

Load growth is highly concentrated, often delayed relative to announcements, and dependent on transmission availability, permitting, water access, and local political alignment. Some regions are pulling ahead quickly. Others, despite strong demand signals, are constrained by grid and siting realities.

For developers, chasing theoretical demand is no longer sufficient. Projects must be aligned with real, executable load pathways, not just macro forecasts.

2. Interconnection has become the primary value driver

Interconnection is no longer a back-office engineering exercise. It is the single biggest determinant of whether a project moves forward and whether it makes money. Small changes in interconnection cost or timing can shift project breakevens materially. Upgrade uncertainty has become one of the top reasons projects stall or die after site control.

In several organized markets, interconnection timelines that once measured in months are now stretching to five to seven years for new generation, fundamentally altering development sequencing and project economics.

In many markets, developers are forced to make go/no-go decisions before definitive interconnection outcomes are known. That elevates the importance of queue-congestion analysis, upgrade sensitivity modeling, and understanding where storage or hybrid configurations can mitigate grid impacts.

Good land without grid advantage is increasingly stranded. Projects that integrate grid realities early are pulling ahead.

3. Solar cannibalization and storage saturation are structural, not cyclical

Merchant assumptions that worked five years ago are breaking down. In high-penetration solar markets, cannibalization is no longer theoretical, it is structural. In the Electric Reliability Council of Texas (ERCOT) North load zone, rapid solar buildout has materially compressed midday pricing, eroding merchant revenues even as total generation capacity continues to grow.

Storage faces a similar reality. Early battery projects captured outsized arbitrage returns, but saturation is already reducing those returns in mature markets.  In the California Independent System Operator (CAISO), increasing battery penetration has driven arbitrage revenues down as competition for the same price spreads intensifies.

This doesn’t mean solar, or storage, are poor investments. It means:

  • Location matters more than ever
  • Revenue stacking must be realistic
  • Modeling must explicitly account for saturation

Projects that ignore these dynamics will underperform. Projects designed around them will continue to attract capital.

4. Storage is the backbone of new power markets – and it comes with new risks

Battery storage is no longer optional. In many regions, it is the economic and operational backbone of new power development.

In 2025 alone, more than 40 giggawatt-hours (GWh) of battery storage was installed in the U.S., with most of that capacity concentrated in CAISO and ERCOT – accelerating both grid flexibility and market saturation.

Storage supports interconnection, manages congestion, smooths intermittency, and enables hybrid configurations. It is also increasingly central to how utilities and large loads think about reliability.

But storage introduces new risks that must be addressed early:

  • Availability and outage risk directly impact revenue
  • Fire codes, setbacks, and safety concerns can halt projects
  • Foreign Entity of Concern (FEOC) compliance and supply-chain uncertainty affect cost and timing
  • Community opposition to Battery Energy Storage Systems (BESS) is increasing

Treating storage as a simple add-on to solar is no longer viable. BESS siting, permitting, and community engagement are now distinct disciplines, and failures in any one of them can derail otherwise strong projects.

5. Data centers are no longer just offtakers — they’re infrastructure partners

One of the most significant shifts underway is how data centers engage with power markets. These customers are creditworthy, often price-insensitive relative to reliability needs, and increasingly willing to co-locate or sponsor generation. Power is no longer an ESG checkbox – it is mission-critical infrastructure.

This shift is most visible in markets such as Northern Virginia, Texas, and parts of the Midwest, where data center demand is reshaping interconnection strategy, site valuation, and development timelines.

Value is moving toward powered land, load-adjacent generation, hybrid front-of-meter and behind-the-meter configurations, and partial islanding models. Developers who understand this shift can unlock new offtake pathways. Those who don’t will struggle to place projects that no longer fit buyer needs.

6. Policy uncertainty isn’t killing projects — it’s killing schedules

Federal policy uncertainty around tax credits, FEOC guidance, permitting, and tariffs is real. But it is not causing widespread project cancellations. What it is doing is elongating timelines and increasing execution risk.

State-level divergence adds another layer of complexity. Some jurisdictions are accelerating capacity additions. Others are increasing scrutiny, particularly around affordability and community impact.

The practical effect is a widening gap between projects that can start construction in 2026 and those that slip into later years, where both pricing and capital availability become far less certain.

The result is a market where speed matters more than ever.

7. The next cycle favors execution discipline over scale

Capital is abundant  but it’s impatient. The market is bifurcating between projects that are executable in the near term and those that are not. Scale alone is no longer enough.

Hybridization is emerging as the default delivery model – combining solar, wind, storage, and, in some cases, natural gas. New greenfield gas faces timing and permitting challenges, while nuclear and Small Modular Reactors (SMRs) remain part of the long-term solution set but face economic and schedule hurdles that limit near-term deployment.

The projects that succeed in 2026 will be those designed around what can be built, not just what looks good on paper.

Where Atwell fits in a market that punishes uncertainty

As these megatrends converge, one thing is clear: the power market is no longer forgiving of late-stage surprises.

Projects no longer fail because the technology doesn’t work. They fail because risk shows up too late – in interconnection, permitting, community response, or execution timing. By the time those issues surface, capital has already moved on.

This is where Atwell’s role has evolved.

We are not just helping clients determine whether a site is technically developable. We are helping them answer whether it is financeable, executable, and aligned with where the market is moving – before significant capital is committed.

That means integrating disciplines that have historically been treated separately:

  • Siting and land strategy, informed by grid and market realities
  • Interconnection intelligence, including upgrade sensitivity and timing risk
  • Policy and permitting risk, evaluated alongside engineering feasibility
  • Community and stakeholder dynamics, addressed early rather than reactively
  • Execution planning, with speed-to-construction treated as a core value driver

In today’s market, those elements cannot be sequenced – they must be designed together.

Speed and certainty are the new competitive advantages

Capital is still available. What’s scarce is confidence. Investors, utilities, and large loads are prioritizing projects that can move quickly with fewer unknowns. The difference between a project that is “possible” and one that is “ready” has never been more valuable.

Atwell’s advantage is helping clients reduce that gap.

Because we work across power generation, storage, transmission, and large-load infrastructure nationwide, we see friction points early – interconnection constraints, permitting triggers, community risk, or schedule killers – and help clients design around them before they become fatal.

In practical terms, that means:

  • Avoiding sites that look good on paper but are unlikely to clear grid or permitting hurdles
  • Prioritizing jurisdictions and configurations where timelines are predictable
  • Structuring projects to be resilient to policy uncertainty rather than dependent on it
  • Supporting hybrid and load-adjacent strategies that reflect how power is being procured today

This approach doesn’t eliminate risk. But it moves risk forward, where it can be managed – instead of discovered after time and capital are already sunk.

A market that rewards realism

In 2026, the power and energy market is entering a phase where realism matters more than optimism.

Projects will continue to be built. Capital will continue to deploy. But the winners will be those who align early with grid reality, policy constraints, and end-user demand – and who can execute with speed and discipline.

That’s the work we are focused on at Atwell: helping clients navigate what’s next, not by chasing headlines, but by building projects that can get across the finish line.

About the Author

Jason Utton

Senior Vice President

Senior Vice President of Atwell’s Power Group, Jason Utton has been developing renewable energy projects for more than 17 years, with experience in wind, solar, and battery storage projects across the country. He currently provides large scale investment and development clients with business goal setting, renewable portfolio optimization, and capital deployment strategies.

The pillars of exceptional client service: Trust, transparency, and teamwork

 

In the engineering and environmental consulting world, technical expertise is table stakes. What truly differentiates exceptional service is the ability to build trust-based relationships that anticipate client needs and deliver seamless support across geographic boundaries and project phases.

For Michael Keith, Project Manager at Atwell, this philosophy has transformed relationships into national partnerships that exemplify the power of collaboration. As projects often represent multiple year commitments, he believes that clients need to know that their project leaders are always engaged and truly understand their goals.

From regional success to national expansion

Keith’s journey with a community solar client began five years ago in Illinois, where he methodically built trust through consistent performance and responsive communication. The relationship didn’t develop overnight—it was the result of steadily doing the right thing, project after project, year after year.

When that same client decided to expand into the Mid-Atlantic states, they returned to Keith with a question that speaks volumes about the relationship he’d cultivated: “Can we take what we’re doing in Illinois and work with your Mid-Atlantic offices?”

The power of institutional knowledge and continuity

This is where Atwell’s integrated, cross-regional structure creates measurable value. Keith didn’t need to hand off the client to a completely new team. Instead, he became the bridge, carrying institutional knowledge from Illinois to new markets while connecting the client with local expertise.

Keith explains. “They can send us a development plan, and we know exactly how they like to receive information and what works within their systems. It took years of refining to get there, but now my team can cover everything they need without them having to even ask.” Keith and his team know the client’s design standards, their financing requirements, and even the specific documentation their financing partner expects to see. This knowledge prevents costly rework and delays.

Consider one example: Keith ensures that eagle and migratory bird evaluations are included upfront, even when they’re not explicitly required for local approvals. Why? Because he knows the client’s financing partner will request this documentation later in the process.

Creating a culture of responsiveness

Keith’s approach to client service is defined by responsiveness and transparency. He strives not to let emails sit for more than one business day, maximum, setting a standard that builds confidence even when immediate answers aren’t available. Creating a team that is deeply connected allows clients to feel confident that things won’t slip. With his colleagues, communication is at the core of client service. “It’s about creating ownership,” Keith says. “I try to bring in other project managers from the start and make it clear: this isn’t my client; this is our client.”

Navigating regional differences

One of the challenges in multi-state projects is understanding how regulatory requirements vary by location. Keith leverages local expertise to navigate these differences effectively. In Illinois, stormwater management focuses primarily on flood prevention. In the Mid-Atlantic, Chesapeake Bay ordinances add layers of water quality requirements that Illinois engineers might not immediately understand.

Rather than forcing one office to learn unfamiliar regulations from scratch, Keith facilitates collaboration. “Anyone can engineer a plan and make water run downhill,” he notes. “But if my Illinois engineers are suddenly dealing with phosphorus removal requirements, they’re reading ordinances for the first time. The Maryland team has spreadsheets ready and can complete the work more quickly.”

This resource-sharing approach ensures clients receive expert service regardless of project location while preventing inefficiencies that inflate costs and timelines.

The support that makes the difference

“It’s the personal touch you give to your clients. All engineers in any company are smart and competent at what they do, but it’s the individual relationships that make the difference and that is what we focus on,” says Keith.

The Atwell approach, national strength, and cross-regional capability are advantages but it’s individual project managers who transform that capability into lasting partnerships. Keith’s clients trust that when they reach out, they’ll get a rapid response, thoughtful guidance, and solutions that reflect a deep understanding of their business.

Keith’s approach demonstrates what strategic partnership looks like in practice. It’s about building relationships that expand naturally as clients grow and as trust deepens. It’s about creating seamless transitions between teams and geographies, so clients experience consistency even as project locations change.

Most importantly, it’s about making the client’s concerns your own and carrying knowledge forward, so every interaction builds on what came before.

In an industry where technical competence is assumed, this commitment to relationships, responsiveness, and collaboration is what transforms good service into an exceptional partnership as clients work with Atwell.

About the Author

Michael Keith

Project Manager

Michael has spent over 20 years solving complex issues in the civil engineering, land development, and renewable power industries by leveraging knowledge of construction and design to create a product that is seamless during construction. He specializes in land development and site civil design in both commercial and residential development and has led engineering teams through the design of site plans, rezoning of properties, drafting preliminary plans, and performing feasibility studies. He works with reviewers, clients, and development team members to ensure projects are delivered on time and on budget. He is also well versed in the implementation of construction inspections and working with contractors to improve field construction issues. 

The 4 Ps of data center development: Power, policy, place, and partnership

By James Hall, Executive Vice President of Special Projects, Atwell, LLC

The demand for digital infrastructure is accelerating at a pace few could have predicted even a decade ago, and data centers sit at the heart of this growth. The success of data center projects depends on how developers anticipate and address two challenges from the very start: access to reliable power and the complexities of regulatory requirements.

These issues are not always the most visible during early planning, but they are almost always the ones that determine whether a project advances smoothly or stalls. Atwell’s integrated approach of combining utility relationships, environmental expertise, and regulatory navigation under one roof gives developers the strategic advantage they need to stay ahead of the data center surge.

Power: Why planning for power and energy comes first

A data center is only as strong as the energy source that supports it. Power is the lifeline of these facilities, and without a robust energy plan, even the most promising sites can quickly fall short.

What makes this challenging is that every region has its own limitations. Some areas face tight transmission capacity, while others may offer ample power today but little room for future expansion. Pricing structures and long-term availability also vary widely. For organizations planning a data center, the question isn’t just, “Is there power now?” but rather, “Will there still be enough 10 years from now?”

The best outcomes I’ve seen come from approaching energy planning as part of the earliest feasibility studies. That means working with utilities, engineers, and planners to understand not just current supply but also the trajectory of regional growth. Because Atwell has relationships with some of the top utility companies both nationally and regionally, we are able to properly plan for energy as soon as possible when it comes to data center development. When clients take this type of long view, they’re far less likely to face surprises down the road. Our early involvement doesn’t just reduce risk; it compresses project timelines by identifying solutions before they become problems or delays.

Policy: Navigating the regulatory maze with an early strategy

If power is the lifeline of a data center, then regulatory approvals are the gatekeepers. Zoning, permitting, environmental reviews, and utility coordination all need to line up before construction can begin. Each of these steps is governed by a mix of local, state, and federal rules, and none of them can be skipped.

This process is rarely simple. Timelines are often longer than expected, and requirements can shift with new policy priorities. Sustainability goals, for instance, are shaping regulations in ways that were not on the radar a few years ago. Communities are also asking tougher questions about how data centers fit into their long-term vision for growth.  Community opposition has and can reroute projects, and this opposition can extend across neighborhoods and state lines quickly. Navigating regulations in the future will involve community engagement as well as regulatory.

The lesson here is that regulatory planning is not something to leave until after a site is chosen; it has to be part of the initial strategy. Understanding the regulatory climate early, from who the decision-makers are to what the community values to where the pressure points lie, helps reduce risk and build momentum.

Place and partnership: Where local knowledge and relationships become a competitive advantage

Both power and regulatory issues are deeply tied to place, but they’re also tied to people. That’s where partnership becomes the fourth critical element—and where Atwell’s approach creates real differentiation.

Communities have their own networks of decision-makers. A permitting path that looks straightforward on paper may be complicated in practice due to conflicts, infrastructure constraints, or environmental sensitivities. On the flip side, opportunities sometimes exist that aren’t obvious to those unfamiliar with the area, such as planned utility upgrades or community initiatives that align with data center investment.

What I’ve found consistently is that our existing relationships, whether with utility executives, regulatory officials, or community leaders, often determine project velocity more than technical specifications. When we’re already a trusted voice in those conversations, our clients benefit from shortened timelines, proactive problem-solving, and access to information that isn’t always publicly available.

This is about being seen as a strategic partner rather than another consultant, not just having contacts. Our clients benefit from relationships we’ve built over decades, local knowledge that can’t be Googled, and the kind of credibility that comes from a track record of successful projects in the region.

The data center industry moves too quickly to build relationships from scratch on every project. When we can leverage existing trust and local knowledge, we extend our client’s reach into communities where they need to succeed.

Staying ahead of the curve in data center development

The data center industry is exploding. The challenges of site selection, power availability, and regulatory approval are becoming more complex as demand increases. That makes it more important than ever to focus on the fundamentals: securing reliable power, navigating regulations with foresight, and understanding the local context. These are not just technical details—they are the foundation on which every successful data center rests. I foresee the following as necessary factors to have in place to keep up with the pace of the industry:

  1. Hyper-scalers will need speed and scale.
  2. Enterprise clients will need reliability and compliance.
  3. Edge operators will need local knowledge and rapid deployment.
  4. Land developers will need the flexibility to position themselves for any of the above.

As the industry evolves, so will the strategies required to deliver these resilient and future-ready facilities. But no matter what changes lie ahead, the three cornerstones—power, regulation, and local knowledge—will continue to shape the path forward.

Learn more about Atwell’s capabilities nationally and locally in mission critical land development consulting here.